Increased electrical capacity in the Free Zone Pirot
The reconstruction of the Tubing transformer station was completed, the high-voltage, low-voltage block, "compensation", measuring group were replaced and increased power of the transformer station for users of the Free Zone Pirot from 170 kW to 400 kW.
By this on December 30, 2022 the first phase of equipping the transformer station was completed. In the second phase, which is expected to be completed in mid-February 2023, a new transformer of 630 kW will be added, which will bring the total power of the substation to 1 MW.